Home / Case Studies / Steel Plant Shutdown reduction by 60 Hrs
96 Hours
36 Hours
60 Hours
62.5%
The Hydraulic Exit Valve Stand-3 serves as a control hub for fluid power supplied to heavy-duty actuators, automatic gauge control cylinders and roll-balancing systems. Its piping network includes pressure lines operating up to 3,000 PSI, return/tank lines and drain lines connected to sensitive proportional valves. The existing system uses seamless ASTM A106 Grade B carbon-steel piping, which had historically required multi-pass welding and post-weld conditioning.
For this replacement, welding presented four major concerns:
The facility replaced the conventional welded joining approach with Pyplok® non-welded radial swage technology.
Pyplok® creates a permanent mechanical connection through controlled 360° radial cold deformation, without welding heat, electrical current or chemical additives. A fitting containing internal elastomeric sealing rings is positioned over a clean, square-cut pipe. A hydraulic swaging tool then applies controlled radial force around the fitting, plastically deforming the fitting and pipe to create a mechanical interlock and compress the internal seals.

Three hydraulic power-unit series were used to accommodate the different pipe sizes across the system:
The high-pressure systems were depressurised and standard safety lockouts were applied. The existing valve stand was mechanically disconnected and removed from the operational area.
The new Valve Stand-3 was structurally anchored. The ASTM A106 pipes were measured and cut square using cold-cutting orbital saws, followed by deburring to ensure clean insertion depths.
The Model 40, 55 and 70 hydraulic tool series were used to complete the required swaged connections. Each joint was checked using a “Go-No-Go” inspection gauge to verify the correct mechanical crimp.
Instrumentation loops were connected and the hydraulic circuit underwent hydrostatic testing at 1.5× the operating threshold. No weeping or micro-leaks were detected, and Stand-3 was subsequently handed over to production.
The biggest outcome was the reduction in the shutdown period.
The complete replacement and commissioning took 36 hours instead of the allocated 96 hours, returning the equipment to production 60 hours earlier than planned. This represents a 62.5% reduction in the allocated shutdown duration.
Beyond the time saving, the cold-work approach also addressed the technical risks associated with welding. No welding heat, sparks or electrical arc were introduced; no welding-related slag, scale or spatter was generated; and the installation avoided thermal distortion. The project also maintained the integrity of connected instrumentation and used immediate mechanical gauge verification for joint quality.
Parameters
Traditional Welding
Pyplok
Joining mechanism
Thermal fusion
Mechanical radial deformation
Heat input
High
None
Internal Contamination
Risk of slag/scale/spatter
No welding contamination
Post-join flushing
Required
Simplified
Quality verification
NDT requirements
Go-No-Go gauge
Execution window
96 hours
36 hours
Marine Heating Coil Repair : Traditional Welding vs. Pyplok® Cold Work
Marine Heating Coil Repair : Traditional Welding vs. Pyplok® Cold Work
Piping for Water Mist System in Dwarka Expressway
Piping for Water Mist System in Dwarka Expressway
Drill Hydraulics Piping for GTRV (Fugro Voyager)
Drill Hydraulics Piping for GTRV (Fugro Voyager)
Kindly provide your details and project requirements, and our team will promptly get in touch with you to address your needs. We look forward to assisting you!