Home / Case Studies / Overcoming the Challenges of Welding in Subterranean Tunnels
8 km
140 bar
25–35%
Traditional high-pressure piping installation relies on processes such as TIG or SMAW welding to create permanent joints.
In an underground tunnel, however, welding introduces challenges across three important areas:
To overcome the limitations associated with conventional welding, the project adopted PreFiS® high-pressure cold-press fittings. Instead of applying heat to the pipe, the fitting is positioned over the pipe ends and permanently deformed using a calibrated hydraulic press tool. This creates a metal-to-metal mechanical seal without welding.

The cold-press approach provided four key advantages for the tunnel application.
The change in joining technology affected more than just the way individual pipe joints were made. By removing welding from the installation process, the project could reduce several activities and resources associated with conventional welded installation.
Parameters
Conventional Welding
PreFiS® Cold Press
Joining method
TIG / SMAW welding
Mechanical cold pressing
Heat input
Required
None
Hot-work requirements
Required
Eliminated
Specialist welding skills
Required
Trained mechanical installation
Joint installation time
45–90 min*
2–5 min*
NDT / post-weld processes
Required
Reduced
Installation environment
More complex in confined areas
Suitable for confined installation
The Samruddhi Mahamarg tunnel project illustrates an important consideration in underground piping: the joining method can have consequences far beyond the joint itself. In a confined subterranean environment, eliminating welding can simultaneously address: Hot Work , Safety Infrastructure, Installation Time , Post-Weld Processes, Total Installed Cost
PreFiS® cold-press technology provided the project with a non-welded method of joining 316L stainless-steel piping for a high-pressure water mist fire protection network, while addressing the installation constraints identified in the project analysis.
As infrastructure moves into increasingly complex underground environments, conventional installation methods can introduce constraints that extend beyond the piping itself. The Samruddhi Mahamarg application demonstrates how non-welded piping technology can be used to address the challenges of hot work, installation speed, material integrity and total project cost in a high-pressure tunnel fire protection application.
20 km Fire Suppression Piping Deployment in Less Than 8 Weeks
20 km Fire Suppression Piping Deployment in Less Than 8 Weeks
Steel Plant Shutdown reduction by 60 Hrs
Steel Plant Shutdown reduction by 60 Hrs
Kindly provide your details and project requirements, and our team will promptly get in touch with you to address your needs. We look forward to assisting you!